Downhill Fireline Construction Checklist

 

Building fireline downhill requires special attention to safety factors because of the potential for rapid uphill fire spread. This Watch Out depicts firefighters building fireline downhill without first mitigating the existing hazards.

9. Building fireline downhill with fire below. Three firefighters use tools to dig fireline down a steep slope covered in grass and brush.  Large flames are below them as the fire burns uphill.

9. Building fireline downhill with fire below.

Read about all 18 Watch Out Situations.

 

Downhill fireline construction is hazardous in steep terrain, fast-burning fuels, or rapidly changing weather. Downhill fireline construction should not be attempted unless there is no tactical alternative. When building downhill fireline:

  • Crew supervisor(s) and fireline overhead must discuss assignments prior to committing personnel. Qualified, responsible overhead individuals such as a Task Force Leader (TFLD) or an Incident Commander Type 4 (ICT4) at minimum, will stay with resources until the job is completed.
  • Decisions about downhill fireline construction will be made only after proposed fireline has been scouted by supervisor(s) of involved crew(s).
  • Lookouts, Communications, Escape Routes, and Safety Zones (LCES) will be coordinated for all personnel involved. This includes verifying:
    • Crew supervisors are in direct contact with lookout(s) who can see the fire.
    • Communication is established between crews.
    • Rapid access to safety zones is ensured in case fire crosses below crews.
  • Direct attack will be used whenever possible; if not possible, the fireline should be completed between anchor points before being fired out.
  • Fireline will not lie in or adjacent to a chute or chimney.
  • Starting point will be anchored for crews building fireline down from the top.
  • Bottom of the fire will be monitored; if the potential exists for the fire to spread, action will be taken to secure the fire edge.
  • Before carrying fire with you, ensure it can be done safely.

 

Last Modified / Reviewed:


Have an idea or feedback?

Share it with the NWCG 6MFS Subcommittee
 


Follow NWCG on X and Facebook
 


 

NWCG Latest Announcements

NEW! Air Operations Summary (ICS 220 WF) Now Available

Date: May 2, 2025
Questions?  Please contact:
National Interagency Aviation Committee

The Air Operations Summary (ICS 220 WF) provides the Air Operations Branch with the number, type, location, and specific assignments of helicopters and air resources. The new ICS 220 WF also includes medical extraction capabilities and air resources tracking.

Understanding the capabilities of aviation assets is critical for effective medical and extraction responses. Coordination with the Medical Unit Leader is essential to ensure alignment and consistency between the ICS 220 WF and the Medical Plan (ICS 206 WF). 

References:

Air Operations Summary (ICS 220 WF)

National Interagency Aviation Committee

Incident Command System (ICS) Forms

Incident Position Standards and Next Generation Position Task Book Available for Firing Boss, Single Resource

Date: April 30, 2025
Questions?  Please contact:
Fuels Management Committee

NWCG is excited to announce that the NWCG Incident Position Standards for Firing Boss, Single Resource, PMS 350-105, and the NWCG Position Task Book for Firing Boss, Single Resource (FIRB), PMS 311-105, are now available. 

These resources, part of the Performance Support Package developed through the Incident Performance and Training Modernization (IPTM) effort, support trainees, qualified personnel, and evaluators. 

Any changes to qualification pathways will take effect with the next update of the NWCG Standards for Wildland Fire Position Qualifications, PMS 310-1.

 

References:

NWCG Firing Boss, Single Resource Position Page

NWCG Incident Position Standards for Firing Boss, Single Resource, PMS 350-105

NWCG Position Task Book for Firing Boss, Single Resource (FIRB), PMS 311-105

Incident Position Standards and Next Generation Position Task Book Available for Helicopter Crewmember

Date: April 28, 2025
Questions?  Please contact:
Interagency Helicopter Operations Subcommittee

NWCG is excited to announce that the NWCG Incident Position Standards for Helicopter Crewmember, PMS 350-22, and the NWCG Position Task Book for Helicopter Crewmember (HECM), PMS 311-22, are now available.

These resources, part of the Performance Support Package developed through the Incident Performance and Training Modernization (IPTM) effort, support trainees, qualified personnel, and evaluators.

Any changes to qualification pathways will take effect with the next update of the NWCG Standards for Wildland Fire Position Qualifications, PMS 310-1.

References:

NWCG Incident Position Standards for Helicopter Crewmember, PMS 350-22

NWCG Incident Position Standards for Helicopter Crewmember, PMS 350-22

NWCG Position Task Book for Helicopter Crewmember (HECM), PMS 311-22

Updated NWCG Standards for Fire Unmanned Aircraft Systems Operations, PMS 515

Date: April 23, 2025
Questions?  Please contact:
Interagency Fire Unmanned Aircraft Systems Subcommittee

The NWCG Standards for Fire Unmanned Aircraft Systems Operations, PMS 515 standardizes processes and procedures for the interagency use of Unmanned Aircraft Systems (UAS), including pilot inspections and approvals. This updated publication provides the aviation community with standards to ensure UAS are used safely, effectively, and efficiently in support of fire management goals and objectives.

References:

NWCG Standards for Fire Unmanned Aircraft Systems Operations, PMS 515

NWCG National Interagency Aviation Committee