SYSTEM:  Helicopter Operations, Personnel (Government)

Sub-System Hazards Pre-Mitigation Mitigation Post-Mitigation

Probability

Severity

Risk Level

Probability

Severity

Risk Level

Policy Operational and mission goals during all-hazard assignments may be unstated or unclear and may conflict with interagency standards and policy

Likely

Critical

Extremely High

Adequate in-brief and dissemination of Commander's intent. Clarification of scope of authority and policy in place.  Adhere to interagency policy, procedures and guidelines (e.g., NSHO). If unable to perform duties utilizing interagency policy, perform a separate risk assessment with appropriate approval sign off. Ensure personnel are working within the scope of their employment. Implementation of Aviation Doctrine may further mitigate conflicts between direction and policy.

Possible

Critical

High

Training Unable to bring seasonals on early enough to provide all the required training prior to sending on incidents

Almost Certain

Critical

Extremely High

Ensure line officers are committed to providing adequate time and funding to develop personnel as necessary.

Possible

Critical

High

Lack of Crew Resource Management (CRM)

Likely

Critical

Extremely High

Provide adequate time for training and provide time for Modules to develop CRM prior to field season.  Provide training in CRM for Modules annually. Brief/debrief, maintain positive attitude.

Possible

Critical

High

Human Factors Fatigue/burnout due to incident duration as well as year-round All Risk incident support

Likely

Critical

Extremely High

Adhere to work/rest guidelines. Monitor fatigue levels of crews. Rotate personnel and helicopter programs to manage fatigue and burnout. Manage number and duration of assignments. Ensure adequate time off and provide quality R and R while on assignments.

Possible

Critical

High

Acceptance of high-risk missions as normal

Likely

Catastrophic

Extremely High

Review risk assessment and existing policy/procedures, brief/debrief with all personnel and utilize risk management tools to include Go-No-Go Checklists. Educate personnel on the hazards of normalization of risk and complacency. Mission decision made at appropriate level. Must have better communication and collaboration between Operations and Aviation.

Unlikely

Catastrophic

High

High workload for Maintenance Inspectors may compromise their ability to perform thorough inspections.  Standard inspections criteria not followed consistently among agencies or regions

Likely

Critical

Extremely High

Increase amount of personnel available to perform the duties of Maintenance Inspector in proportion with span of control. Ensure inspection standards are developed and maintained by agencies.

Unlikely

Critical

Medium

Conflicting personalities resulting in hazardous attitudes

Possible

Critical

High

If individuals cannot professionally resolve differences, managers and supervisors must intervene immediately. Brief/debrief, employ CRM, provide honest and objective feedback, maintain positive attitude. Maintain professionalism and mission focus at all times.

Unlikely

Critical

Medium

 

Download the Word version (docx) of this information and the Risk Assessment Matrix (pdf) to use with the Risk Assessment Worksheet (docx).

 

 

Modified / Reviewed:

NWCG Latest Announcements

NWCG Equipment Technology Committee Releases Safety Warning: 25-001 Non-specification fire shelters

Date: January 15, 2025
Contact: Equipment Technology Committee

The Equipment Technology Committee (ETC) has released Safety Warning: 25-001 Non-specification fire shelters. Non-specification fire shelters claiming to meet Forest Service (FS) fire shelter specification 5100-606 were first found in February of 2023. As of September 2024, non-specification shelters are again being advertised and sold on the open market.

This Safety Warning outlines details and recommended procedures to purchase FS specification shelters made with materials and components that meet performance criteria and toxicity testing requirements outlined in FS Specification 5100-606. 

For additional information on identifying non-specification shelters, please view ETC Safety Warning 23-01.

References:

ETC Safety Warning 25-001: Non-specification fire shelters

NWCG Equipment Technology Committee

ETC Safety Warning 23-01

Paul Gleason Lead by Example Awards

Date: January 14, 2025
Contact: Leadership Committee

The NWCG Leadership Committee has awarded the 2023 Paul Gleason “Lead By Example” awards to individuals in the categories of Initiative and Innovation, Mentoring and Teamwork, and Motivation and Vision, as well as a Lifetime Achievement Award.

Congratulations to the awardees:

  • Sam Bowen, Superintendent of the Mark Twain Veteran Crew with the U.S. Forest Service.
  • Greg Titus, Zone Fire Management Officer for the St. Marks National Wildlife Refuge with U.S. Fish and Wildlife Service.
  • Renae Crippen, Manager of the Blue Mountain Interagency Dispatch Center with the U.S. Forest Service.
  • Eric Carlson, Instructor with OMNA International.

References:

Paul Gleason Lead by Example Award

Wildland Fire Leadership Development Program

Interview with Paul Gleason

Updated NWCG Standards for Water Scooping Operations, PMS 518

Date: December 19, 2024
Contact: Water Scooper Operations Unit

The NWCG Standards for Water Scooping Operations, PMS 518 establishes the standards for dispatching, utilizing, and coordinating water scooping aircraft on interagency wildland fires. These standards should be used in conjunction with the NWCG Standards for Aerial Supervision (SAS), PMS 505, and any local, state, or geographic/regional water scooping plans.

References:

NWCG Standards for Water Scooping Operations, PMS 518

Updated NWCG Standards for Aerial Supervision, PMS 505

Date: December 19, 2024
Contact: Interagency Aerial Supervision Subcommittee

The Interagency Aerial Supervision Subcommittee has updated the NWCG Standards for Aerial Supervision, PMS 505. PMS 505 establishes standards for aerial supervision operations for national interagency wildland fire operations. 

References:

NWCG Standards for Aerial Supervision, PMS 505